All of a building’s consumption in one system

Metering collects readings, analytics finds waste, automation fixes schedules, and reports show the owner the result. The modules share the same data and all come with the subscription.

01 · Metering

Consumption by floor and system

Every metering point is mapped to a building, a floor and a system, so the same consumption can be broken down by floor or by engineering system.

Electricity is polled every 5 minutes and heat meters every hour. History is kept for 5 years.

  • Electricity, heat and water
  • Virtual meters: sums and differences of points
  • Communication monitoring for every device

Consumption on a weekday, kWh

Daily consumption by floor and system
Roof and plant floor2,05038%
Floor 554010%
Floor 458011%
Floor 354010%
Floor 2, server room1,01019%
Floor 1 and car park66012%
  • HVAC
  • Lighting
  • IT and server room
  • Sockets
  • Lifts and pumps

Total for the day: 5,380 kWh

02 · Analytics

Anomalies priced in dollars

For each day of the week Vatt builds a normal, weather-adjusted demand profile and compares actual data with it.

Each anomaly lands in a feed with a waste estimate, an owner and a status, so nothing gets lost between maintenance shifts.

  • Rules for night load, weekends, peaks and tan φ
  • Baseline adjusted for outdoor temperature
  • Notifications by e-mail and Telegram

Weekly anomaly feed

  1. Mon

    02:10Night load 18% above normal

    210 kWhResolved

  2. Tue

    08:15356 kW peak at chiller start-up

    capacityNeeds a decision

  3. Wed

    11:00Heating and cooling at once, floor 4

    84 kWhIn progress

  4. Thu

    21:40Car park lighting on after 9 p.m.

    46 kWhResolved

  5. Sat

    07:30Climate running on the weekday schedule

    780 kWhIn progress

  6. Sun

    14:00Meter DB-3.2 offline for 40 minutes

    data flaggedFor information

03 · Automation

Schedules that are actually followed

Climate and lighting schedules are set by zone and day of the week. Vatt writes them to controllers over BACnet or Modbus and checks against the meters that equipment really switched off.

Writing is enabled per device after sign-off from the maintenance team. Every change is recorded in the audit log.

  • Public holidays from your country’s calendar
  • Evening extensions on a tenant’s request
  • Roll back to the previous schedule

HVAC schedule, offices on floors 2–5

Working days

Mon
Tue
Wed
Thu
Fri
Sat
Sun
  • People in the building 09:00–19:00
  • Before 05:00–23:00
  • After 07:30–19:30

Climate running time per week: 126 h before, 60 h after.

Mark a day as working or off and the schedule is recalculated.

04 · Reports

A monthly report for the owner

The report is assembled on the first working day of the month: consumption and cost by building, weather-adjusted comparison with last year, detected waste and the effect of measures taken.

  • PDF and XLSX
  • Export via API
  • Cost allocation between tenants by meter

Sample report

PDF · XLSX · API

Office centre, 12,400 m²

Monthly report · August 2026

Consumption
158,400 kWh
−6.2% vs August 2025, weather-adjusted
Cost
$22,200
at $0.14 per kWh
Waste found
9,400 kWh
8 anomalies, 6 of them resolved

Consumption by week in August, MWh

See the modules on data from a similar building